We’re making great progress at Trassaco Park! Site setup, including stores, offices, and temporary power, is complete. Site clearance and demolition are done. The boundary fence wall is advancing, with foundations finished, columns at 90%, blockwork at 85%, and plastering at 60%.
Block 01 has completed excavation and blinding, with column bases and strip footing at 90%. Block 02 is at 100% excavation and 80% blinding.
In June, we’ll begin blockwork, MEP fixings, and slab work for Blocks 01, 02, and 03. Check out the photos below and stay tuned for more updates!